We’re making excellent progress on a major three-stage redevelopment at De La Salle College in Māngere.
The two-year project involves demolishing old classrooms, constructing a new classroom block and refurbishing adjacent blocks, as well as associated civil works and landscaping.
The work is taking place in three separable portions to minimise disruption to the school community, and so students can move into the new block while the third stage progresses.
The new classroom facility block has some complex structural elements in response to challenging ground conditions, and required more than 60 steel piles to be driven 30m into the ground to support the load of the three-level steel and concrete structure.
Site work is tracking on programme for completion by April 2025.
We’re making excellent progress on a major three-stage redevelopment at De La Salle College in Māngere.
The two-year project involves demolishing old classrooms, constructing a new classroom block and refurbishing adjacent blocks, as well as associated civil works and landscaping.
The work is taking place in three separable portions to minimise disruption to the school community, and so students can move into the new block while the third stage progresses.
The new classroom facility block has some complex structural elements in response to challenging ground conditions, and required more than 60 steel piles to be driven 30m into the ground to support the load of the three-level steel and concrete structure.
Site work is tracking on programme for completion by April 2025.